![]() |
Residential Architect help needed..
We are currently in the process of re-doing our house and have been talking to an architect to help design it...
My question is,how do you pay the architect ? He wants 7% of the total project with the following breakdown. a)-Concept 15% b)-Drawing 15-20% c)-Construction documents 35% d)-Construction 25% The project will be well into $300,000+ .... I asked him about the differences in clause c and d and he couldn't come up with a concrete answer... The problem is,yesterday he brought some detailed drawings of the concept we have worked up along with an invoice of $7000 :mad: We have always told him that we first need to get a floor plan so that we can discuss it with a builder to see if this project is even with in our budget or not.. and he is,all worked up with 3-D images of the house with the floor plans that we didn't even like... Please guide.. Thanks |
Well if he has done work without a mutual agreement then he's ***** outa luck.
Don't know about how they normally bill but his actions so far would make me hesitant. Yes he may be eager/excited/motivated but if he does not listen to the client then what good is it. You know there are a couple of Architects here on the board that might be interested in the work. Good luck. |
I would never go for a percentage of costs. There is no incentive for architect to save you money, it will be in his best interest to over-design all structure & finishes, etc... Plus, if you upgrade granite/cabinets/appliances/tile... the 'big ticket items' there is no additional work for the architect.
I pay by the square foot for new plans/new construction, but that is totally different. Having said that, a good architect can easily save you money. Try to get recommendations. You should be able to scope out the work, and get a fixed price. Be sure ask about addition costs like as-builts and field changes. |
RE:
a)-Concept 15% b)-Drawing 15-20% c)-Construction documents 35% d)-Construction 25% I don't want to quibble about labels but some architects might have done it this way. a)-Preliminary Design 25% b)-Schematic Design 15% c)-Construction Documents 50% d)-Construction Observation 5% This is weighted more in the architects favor and less towards actual experience. It's front loaded in case the project gets put on hold, or the owner takes over construction observation to save a few bucks at the near the end. The 7% is in line with the lower end of fees. If you are not willing to pay around the same the state is making on sales tax (in Michigan 6%) you are not allowing the architect to do a good job (or redo in this case). Since you know the project costs (more or less) you may make the fee fixed, but remember extra work and changes into the CD period will have to be paid for. Design is about making decisions and choices. If someone brings you one design, they are offering no choice and no decision making process. If this is some famous architect branding his work with a cookie cutter and you are acting as his patron saint, then great. However most architects are a service professionals. Imagine a chef creating a custom meal for you and your family, and NOT a waiter talking your order off a menu. 1. I listen, interpet and generate alternates to consider. 2. The initinal product or "concept sketches" will be three basic different ideas, with a couple of variants on each (freehand on tracing paper). we sit down, throw a few schemes out (while the owners is screaming; YOU ARE NOT LISTENING TO US), combine a few more and meet again with it drafted out on Autocad or a refined hand drawing. We are still in the first phase. I try to remember that the owner is asking for help defining the problem and solving the design problem (even when the owner says; we know exactly what we want). If there was no problem, there would be no work, and a draftsperson could just do it. Tell the architect to come back with three to six rough floor plans (not perfect, just ideas), you are right to start with the floor plans, but someone (the architect) should be steering the ship towards friendly massing and final looks in the back of his head, and at all times. I hope this helps. I'm not registered in Kentucky, good luck.:) |
Quote:
Thanks |
Quote:
Even a one page contract is better than nothing, defines the work and helps prevent misunderstandings later. Is he designing the kitchen? Is he doing interior elevations of all major rooms or features? Has he included structural engineer fees and his other possible costs? The more work, the higher the fee. The more time spent in preliminary design, the more pressure to do skimpy bare bones CD's. |
Quote:
Architect: 16 hours at $70/hour ..........................$1150) Design guy ( planning ) 72 hours at $45/hr..........$3240 Over head: .................................................. ........$2300 Profit at 10%: .................................................. ....$650 Total:............................................ ............$7200 ( approx ) The problem is....we are still no where near the end of the drawing phase and we already have the invoice for $7500....Where would this end ? |
Quote:
Thanks |
$70/hr for an architect in my neck of the woods is dirt cheap. I am used to seeing $125 or more.
I'd suggest you have this conversation with your architect, not us. You should have had some understanding of the process at the beginning. If not, get with him and work it out. I'd get happy with the concept sketches before any sort of detail designs or renderings were done. No point in going down a dead end. All of my experience with architects and owners "who know what they want" leads me to the following observation. An architect's job is to give the owner something that he needs and makes him happy in the end, not what he asks for in the beginning. I haven't met an owner yet that had any sort of good ideas on layout. A good architect will show an owner lots of things he'd never figure out on his own and avoid all of the fruitless ideas that go nowhere. If this project were mine, I'd figure that I owe the guy what's on the bill. It's too late to negotiate the price on what's already been done. JR |
Quote:
JR |
Quote:
I've had clients ask for all sorts of renderings and models which were not in the contract. Yes, same people who know exactly what they want. I told them show me the money, they said let's work it out. In lieu of putting the project on computer I hand drafted on 11x17 photocopies from their original prints they had. I was able to put more time in design, and less into CD's because they cared about understanding the design and having the house right more than the paper I produced. We were only able to pull this off because the builder and I had done 20 projects together already and worked as a team. math: 300,000 x .07 = $21,000 21,000/50 (approx rate) = 420 hours He has approx. 420 hours to get the job done, use up half on design (210 hours) and you have another 210 hours to do the drawings and put out all the fires during construction. Now if preliminary design/concept design is done, the total so far would be 21k x .15 = $3,150 Ask him why he has invoiced you for approx double agreeded, and let him know you are not happy with the concept so far. You might pay him half and get him to do more work. Or you could see him in small claims court so you can tell your side of the story to a judge. |
Quote:
While the hourly prices seem fair at first glance, he is effectively raising them by adding overhead & profit. You are really paying an average of $7500/88hours = $85/hour. I pay alot of professionals hourly....lawyers, engineers & architects. Never been billed this way, adding overhead and profit. They build it into their base hourly fee. How was overhead calculated? % of total bill? How was this quoted originally? It seems he is using %of total, profit, expense, hourly, whatever is highest..... kach22i - Good info. Have you ever seen hourly + overhead + profit billing? |
Fixed price contract.
|
Quote:
Profit? What's that? If he works out of his house and does all the work himself it's all profit. Assuming overhead is his choice, not yours. Strange bill, does not mean he does not know what he's doing. I think he is a better business man than me, he has figured out a way to make money as an architect.:D EDIT: Lot's of Cost-Plus-a-Fee contracts with architects using a Google Search. I've never used one, it's frak'n residential for gosh sakes. http://www.google.com/search?pz=1&ned=us&hl=en&q=cost+plus+contract+arch itect&btnmeta%3Dsearch%3Dsearch=Search+the+Web |
Thanks a lot guys..
Anyways,i had told the architect from the get go that the budget should be under $300,000 and i guess he calculated all his fees from there.. Last night told him not to make any more drawings :D until he sits down with the builder to see what the rough estimate would be ..once we know the cost is with in the budget,then i will go ahead and give him a green light for further 3-D drawings.. Bottom line is,i need to tell him i don't want to do a % of the total cost as that could be skewed...Fixed contract is what he is going to get :D Please keep the suggestions coming. Thanks |
Make sure you select a good architect based on experience, reputation, and completed projects. There are a lot of inexperienced people out there that pretend to be all this and that, and may try to dazzle you with cute renderings, but don't really have a clue of structural engineering, construction methods, and how to design plans that will glide though the approval process and plan check, and if they can't get you the permit, they are nothing more than a draftsman and that is all he is worth. Without that the delays will frustrate you, and the construction problems, continual professional consultations, and change orders can cost you 2-5 times or more of what you spent on the architect. Ask the counter guys at plan check in your city what their experience has been with a particular architect or engineer - their feedback will be very enlightening.
|
I don't like what I see here. If the design is not to your liking and he was not cleared to go in the direction that he went, I'd agree to pay the bill when the design is approved, not shoved down your throat.
He should have shown you preliminary workups in a CAD program before committing to a more detailed plan. He should also be able to to design around your budget and give you a budget breakdown along with the concepts. ........................... There seems to be a difference in opinion here about the observation of construction and how much the architect should be paid and be involved. I've always heard that if you have a strong architect and a strong builder, there will be a clash. Not that having the opposite would be a good thing. But, it would be nice to know that one or the other can give some ground. A strong builder can overcome architectural problems thru shear experience. And, there will be problems. If there is some fee left in the agreement for construction observation, make sure the architect has agreed to provide modified drawings as needed. On my last big job, we ran into unknown and concealed problems. Half of those were the result of the engineer not surveying the existing home thoroughly. For instance, his drawings showed and were dependent on a concrete footing that was never there. When demolition started and he saw the omission, he corrected his plans and charged for that. Right there, I blew my top at the guy and told him that I wouldn't work with his kind. Didn't matter as he continued to "find" problems and amend his plans and refile them with the city. The thing is, some of these changes affected the design and involved the architect who had to revise his drawings to fit the engineering changes. Since he was the one to refer the engineer, he went soft on his rework. The very first day I had the plans, I removed the staples and regrouped the sheets. I placed each engineering sheet under each floor's plan view and found things that didn't line up or were completely outside of the walls! I did this over a glass table with a halogen light below. Then, I lined up the floors of each set to find even more errors. When you get you plans, don't be so quick to dig. |
Quote:
Contractors charge more for the unknown and changes, so do architects. Such is the risk to the owner of an existing building. What has happened in the past is I have not charged for my extra time if it is with in reason, most small jobs will have an extra day's worth of unexpected changes to them, I build it into the price. The General Contractor may waive his time to solve the problem and not mark up the new work. For example we had to add helical piers to a foundation because of poor soil (foundation inspector caught it - permits are a good thing) after the owner insisted the soil was great from the start of the project - it's baby poop (soil testers exact words). I found the lowest cost soil tester and helical pier contractor - no reward other than a happy client. |
Quote:
The thing is, the engineer told the owner he CRAWLED under there. And then he had to balls to tell me he crawled under. I knew that was a bald face lie, told him so and told him to not ever get within striking distance of me. I don't take being lied to very well at all. In fact, one lie and you're out of my life forever. This was the poorest performance of any licensed person I have ever dealt with. Then, to come back with an invoice on top of the lie was even more incredible. I know now why some people get so aggravated that they end up being charged with assault. I could still throw that guy off the roof. Such is the risk to the owner of an existing building" That is really a poor statement. |
You CAN discover almost everything, if the client wants to spend enough money, up front. Few do. Hopefully they are realistic and understand that if they didn't spend tons of money on the site investigation prior to the design, unforseen things will be dealt with in a sensible manner.
I don't pad my bid for "unknown items" but I also don't ream the owner for change orders. In fact, I hate change orders. I probably do a little more investigation during the bid process than just about anybody you know. JR |
A few years ago, my crews uncovered about 500 ft of railroad track that ran straight across a site I started construction on - that and an unknown underground tank - talk about a discovery! :) :)
|
Quote:
Can we get down to basics? 1) You are the Client who is asking a professional to assist you in re-doing your home. 2) You, with his/her help need to explore what it is you aspire (or want) to achieve by this project. 3) The exploration is led by the architect who asks you the 'correct' questions which help you define what it is you want. The reality is that in asking the right questions you will all discover options ideas that where not thought of at the beginning and will ultimately be more satisfactory than the starting point. The Client who has such a fixed idea of what they 'know' they want is the one who is going to get it wrong and make a hash of things. 4) The process is both verbal and graphic..sketches, diagrams, simple 3D views etc to help direct that process.The more you put in here the less the project will cost you and the less you will spend on fees as the result of this process will be far firmer and less subject to change. 5) Payment. If you were to come to me I'd do a fixed sum for these initial concept stages.. say $5000 to deliver an agreed concept, some scaled hand drawings etc all in a report that you or the architect can take to contractors etc for price guide (not cost) to the planners etc to make sure there are no show stoppers. 6) With you having agreed or signed off on that concept and an outline cost then you do go to a percentage fee, especially on refurb work. If you insist on the fixed price you are saying that regardless of lack of information (are you paying for survey work? Opening up of floors? Walls etc to derisk the process...) the architect will have a set amount of money. He will ration that quantum in the design phase as he controls that the most.. allowing the balance on site and a lot in reserve for potential changes. All in all you are spending money to correct potential cock-ups, rather than spending money to avoid them in the first place. Either way the only sufferer will be you. The breakdown of the detailed design and then construction information is somewhat flexible but do not skim on this as its not money saved... you will spend all of it and more on correcting errors, omissions, alterations or legal fees sueing the architect. So save yourself the aggravation and ensure there is a sufficient monies in there to do the job correctly. 7) Play hardball now on fees (and save perhaps 10%) on paper and spend an extra 25% of the budget on cock up correction and additional fees...not good economics. I would suggest that you ask the architect to define how he has resourced the job in the different phases; we show the client a timeline chart that shows who is working at the job at all times and for how much time...it helps to understand a monthly invoice if you know you have been paying for two people full time for that month...it makes you realise why the invoice is high and you know if you are getting value for money. 8) On a refurb job make sure the architect is employed during the site time. Again its a relatively inexpensive insurance policy...and a good, strong architect will listen to the skilled experienced contractor and find a solution that takes his/her design intent and the contractor's experience to create the correct solution. 9) You are the Client, you do need to take responsiblity for your choices, in contractual terms, in setting an acceptable cash flow solution which enables the architect to do the work without 'funding' you, in accepting/ rejecting work in a clear and timely manner and in making decisions and sticking by them. 10) Remember anything and everything is possible. Just how much time and money do you have? Sorry its long, but over the years I have spent some very happy times helping private clients build their 'dream homes' and some very trying times with professional clients who are trying to skim on design time... yet fail to see how much money correcting site issues costs compared to design cost. (At the rates he is quoting I cannot imagine how he makes a living...!) And the only important thing.. this is supposed to be exciting and fun, for you and the architect otherwise its not worth it. |
Well said.
BTW, that date in your sig line is interesting: 13/03/09; I guess Dueller is in another dimension. ;) |
Thanks to every one who took time and responded to my question..I will be meeting with the architect today and will let you guys know how it went...
Thanks once again.. |
Quote:
As far as I know, we're the only ones that use the month/day/year. |
Quote:
|
Question for Architects
How long ( time wise ) and tidious ( involving ) is the process in making a sketch to say a design that gives you the room measurments/elevations ?
Thanks |
Quote:
Most of my custom home additions take a full day to mark-up. I often come back to double check one or two detail items. At this point you still will not have a "to scale" base sheet in which to do design studies on, things must be drawn up either by hand or put on computer. Again this may vary from a day (carport job with no interior) to several weeks (could be a month if stretched out because of other projects). If the project is just an addition pretty much separate from the rest of the house then a cut off line or break line ignoring the parts of the house unaffected by the work is a shortcut (not to be used in your case from what I know) commonly used. On small projects where the design is simple and straight foreword, just putting all of the existing house to scale is half the work and time spent. On larger more complex projects the set-up time for base sheets may be a small fraction of total project time spent. Documenting the existing house right will save time, money and problems later. Working off an existing set of plans without painstaking verification is an accident waiting to happen. I've never seen or been given an accurated as-built set, never. I want to say that I've had clients in which some outside influence was whispering conflicting advice (and dangerous misconceptions). As an architect I see my job as making my client happy, not some invisible force creating mischief in my project. Questions are welcomed, but micromanagement is not. Anyone can become anxiety ridden when given conflicting opinions. I fear that my opinion which is based on not seeing your project is pretty much weightless in this situation. Weight that as you will. |
Quote:
FYI I am a licensed archiect that belongs to the AIA and is NCARB certified and LEED Accredited Professional. |
All times are GMT -8. The time now is 11:31 AM. |
Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2025, vBulletin Solutions, Inc.
Search Engine Optimization by vBSEO 3.6.0
Copyright 2025 Pelican Parts, LLC - Posts may be archived for display on the Pelican Parts Website