Quote For Engine Rebuild
Guys,
I am in the process of doing a rebuild on a 2.4T motor which will be rebuilt using 2.2S P&C's, 2.2/2.4S heads, and S MFI cams which I have been gathering for the past year. The S MFI is complete and need nothing.
Upon inspection of the parts I was told that the crank was good and the heads need a valve job and new valve seats. He hasn't advised yet if the P&C's need any work. I will find out in the next day.
Anyway, below is his quote. Does his pricing seem reasonable?
Also, what is the typical number of hours required to do a rebuild? He has quoted me 48 hours which seems high considering that he is only putting the motor together (the engine was give to him already apart)
Does this estimate seem fair?
Lastly, I wonder what would need to be done by a machine shop to the rods that would cost $310. Does rod bushing replacement cost this much? What other machine work could they do?
Parts /Sublet / Labor
Parts;
main bearings 175
rod bearings 66
chain rail set 68
intermedaite shaft bearing set 69
cam chains 110
upper/lower gasket set 245
oil return tubes 85
6 exhaust valves 480
6 inatke valves 312
bronze phous silica guides 75
6 flywheel bolts 74
connecting rod bolts & nuts 230
OEM ring set 290
misc. (MFI belts/ fan /hardware) 240
Sublet:
crankshaft polish & mic 95
cylinder head recondition 675
guides/ decarbon /cut seats/
install spring hts.
remachine connecting rods 310
Labor:
48 hrs. @ 80 per 3840
|