Quote:
Originally Posted by rfuerst911sc
I plan on pouring two pads 24 " x 24 " about 10 " thick for the lift posts and the rest of the floor will be about 5 " - 5.50 " thick .
|
Is this going to be a monolithic pour are are you actually pouring two pads and then surrounding with the remaining pad? I had my cement installer dig out two areas about 3' sq each so the pads would be about 7-8" deep in that area and 5" or so the remaining pad.