How much to install 12x12 wall tile?

I have a cousin who has been doing some tile work for me. I've been paying her $7 a sq ft for installing floor tile. Above the local rate, but hey, she's my younger cousin, and does great work.

I need to her to install some 12x12 that match the floor in the bathroom, and then a pencil/tile/chair rail detail on top. The 12x12 need to go in before I will have the detail tiles in hand (need to finish my plumbing trim out), so I'm going to pay her for that alone.

Same price as floor?

Any idea how much I should be paying her for the detail on top?

__________________
2022 Royal Enfield Interceptor.
2012 Harley Davidson Road King
2014 Triumph Bonneville T100.
2014 Cayman S, PDK.
Mercedes E350 family truckster.
Old 07-30-2012, 10:07 AM
  Pelican Parts Catalog | Tech Articles | Promos & Specials    Reply With Quote #1 (permalink)
Registered
 
Join Date: Mar 2009
Location: KINGSTON,PA
Posts: 1,642
I'm not a contractor, but have had alot of tile work done at my cabin. ( over 5000 sq ft of work)
Detail work was paid at 1.25-1.5x the flat sq ft rate.
__________________
94 turbo 3.6
74 carrera RS race car
05 denali XL
"We are here to laugh at the odds and live our lives so well that Death will tremble to take us." Charles Bukowski
Old 07-30-2012, 10:15 AM
  Pelican Parts Catalog | Tech Articles | Promos & Specials    Reply With Quote #2 (permalink)
JW Apostate
 
trekkor's Avatar
 
Join Date: May 2004
Location: Napa, Ca
Posts: 14,164
Why pay by the sq ft?

I have never worked by the square foot.



KT
__________________
'74 914-6 2.6 SS #746
'01 Boxster
Old 07-30-2012, 10:46 AM
  Pelican Parts Catalog | Tech Articles | Promos & Specials    Reply With Quote #3 (permalink)
Registered
 
Join Date: Mar 2009
Location: KINGSTON,PA
Posts: 1,642
Every contractor that came to quote me a price measured the area of the job. After material was factored in and a price given i would divide the price by the sq ft of the job to give me a dollar cost per sq ft. Perhaps the contractor wasn't figuring price per sq ft but i used my calculation to compare contractor a to contractor b, etc.
__________________
94 turbo 3.6
74 carrera RS race car
05 denali XL
"We are here to laugh at the odds and live our lives so well that Death will tremble to take us." Charles Bukowski
Old 07-30-2012, 10:58 AM
  Pelican Parts Catalog | Tech Articles | Promos & Specials    Reply With Quote #4 (permalink)
Registered
 
Zeke's Avatar
 
Join Date: Jan 2002
Location: Long Beach CA, the sewer by the sea.
Posts: 37,695
Quote:
Originally Posted by matt f View Post
Every contractor that came to quote me a price measured the area of the job. After material was factored in and a price given i would divide the price by the sq ft of the job to give me a dollar cost per sq ft. Perhaps the contractor wasn't figuring price per sq ft but i used my calculation to compare contractor a to contractor b, etc.
Not a bad method as long as the area and conditions are exact. Change anything and the per sq ft price will change. So, sq ft prices are fine for airports where area trumps most everything.

$ per sq ft is a guide only. It is very useful to make sure prices calculated are what they are supposed to be. In the end, though, it's the job that is being priced because the same job at another house may cost more or less.
Old 07-30-2012, 12:38 PM
  Pelican Parts Catalog | Tech Articles | Promos & Specials    Reply With Quote #5 (permalink)
JW Apostate
 
trekkor's Avatar
 
Join Date: May 2004
Location: Napa, Ca
Posts: 14,164
I've had people call my office many times asking for a square foot price.
I don't have one. I won't ever give one.

I measure the job, determine the cost of materials and construction methods I am going to use and the TOTAL amount of time I am going to spend doing the job.

If you want to come up with a "square foot" price based on that, fine.

I can set 3-400 square feet of ceramic 12x12 floor tile over a flawless, wide open, surface in a day, no problem.
Add surface defects, door ways, hall ways, cabinets, floor registers, walls out of square, diagonal layout, etc, and I may not even get 100 feet down.

Bidding by the square foot is what a production shop will do.
Fast work is usually low quality.


KT
__________________
'74 914-6 2.6 SS #746
'01 Boxster
Old 07-30-2012, 01:02 PM
  Pelican Parts Catalog | Tech Articles | Promos & Specials    Reply With Quote #6 (permalink)
 
Registered
 
Join Date: Mar 2009
Location: KINGSTON,PA
Posts: 1,642
Quote:
Originally Posted by Zeke View Post
Not a bad method as long as the area and conditions are exact. Change anything and the per sq ft price will change. So, sq ft prices are fine for airports where area trumps most everything.

$ per sq ft is a guide only. It is very useful to make sure prices calculated are what they are supposed to be. In the end, though, it's the job that is being priced because the same job at another house may cost more or less.
The quotes i am comparing are for exactly the same job. I break itdown to sq ft pricing to explain to equally qualified bidders why i chose the contractor i did. Black and white, no fuss.
__________________
94 turbo 3.6
74 carrera RS race car
05 denali XL
"We are here to laugh at the odds and live our lives so well that Death will tremble to take us." Charles Bukowski
Old 07-30-2012, 01:56 PM
  Pelican Parts Catalog | Tech Articles | Promos & Specials    Reply With Quote #7 (permalink)
You do not have permissi
 
john70t's Avatar
 
Join Date: Aug 2001
Location: midwest
Posts: 39,853
I thought labor was usually 20-30% of the entire job, so I just guessing this could be close to ballpark pricing if nicer tiles are being used.

Take measurement of the room in feet and multiply by 7 to find labor.

Make absolutely sure the shower floor and ledges are leveled to drain all water into the drain, and that the drain/plumbing is installed and sealed correctly.
Grout has to be complete and sealed.
That stuff can destroy houses.


It's a relatively small job, and a family member doing it right.
What was the question?

Last edited by john70t; 07-30-2012 at 06:35 PM..
Old 07-30-2012, 06:28 PM
  Pelican Parts Catalog | Tech Articles | Promos & Specials    Reply With Quote #8 (permalink)
Registered User
 
Join Date: Jul 2012
Posts: 8
Every contractor that came to quote me a price measured the area of the job
Old 07-30-2012, 07:12 PM
  Pelican Parts Catalog | Tech Articles | Promos & Specials    Reply With Quote #9 (permalink)
JW Apostate
 
trekkor's Avatar
 
Join Date: May 2004
Location: Napa, Ca
Posts: 14,164
Quote:
Originally Posted by ElmerBento View Post
Every contractor that came to quote me a price measured the area of the job
Of course we do, but it would absurd to apply a square foot multiplier to produce a price.


A 30 square foot backsplash could take as long as a 60 square foot bathroom floor or a 200 square foot kitchen floor...


KT
__________________
'74 914-6 2.6 SS #746
'01 Boxster
Old 07-30-2012, 07:38 PM
  Pelican Parts Catalog | Tech Articles | Promos & Specials    Reply With Quote #10 (permalink)
Parrothead member
 
VINMAN's Avatar
 
Join Date: Jul 2003
Location: Monmouth county, NJ USA
Posts: 13,832
I'm in the same line of thinking as Trekkor . I give my customers prices based on the work involved, not the size of the job There are always too many variables Especially with bathroom remodeling
__________________
Vinny
Red '86 944, 05 Ford Super Duty Dually '02 Ram 3500 Diesel 4x4 Dually, '07Jeep Wrangler '62 Mercury Meteor '90 Harley 1200 XL
"Live your Life in such a way that the Westboro Baptist Church will want to picket your funeral."
Old 07-31-2012, 04:33 AM
  Pelican Parts Catalog | Tech Articles | Promos & Specials    Reply With Quote #11 (permalink)
Slackerous Maximus
 
HardDrive's Avatar
 
Join Date: Apr 2005
Location: Columbus, OH
Posts: 18,164
Thanks guys.

__________________
2022 Royal Enfield Interceptor.
2012 Harley Davidson Road King
2014 Triumph Bonneville T100.
2014 Cayman S, PDK.
Mercedes E350 family truckster.
Old 07-31-2012, 08:46 AM
  Pelican Parts Catalog | Tech Articles | Promos & Specials    Reply With Quote #12 (permalink)
 
Reply


 


All times are GMT -8. The time now is 11:59 PM.


 
Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2025, vBulletin Solutions, Inc.
Search Engine Optimization by vBSEO 3.6.0
Copyright 2025 Pelican Parts, LLC - Posts may be archived for display on the Pelican Parts Website -    DMCA Registered Agent Contact Page
 

DTO Garage Plus vBulletin Plugins by Drive Thru Online, Inc.