Quote:
Originally Posted by BK911
I appreciate the concern.
It's 12" block with rebar every 2' and filled with concrete.
A multi layered rubberized water proof coating is on all under grade block.
The structure sits about 200' away from the lake and about 50' above the top of the dam.
Above the structure is a pretty thick forest and only about another 100' elevation increase over a mile or so.
So zero threat of a flood, and highly unlikely mud slide.
Hopefully!!!
|
Make sure you put a drain pipe to collect water including gravel around the foundation to remove any ground water that builds up.
__________________
Chris
89 930, 87 930, 86 930 Ruf BTR tribute, 89 Ruf CTR tribute
|