Finally done - finished the last bit of the path on Sunday.

Expense breakdown:
  • Prep, including having the old patio removed, french drains, etc: $2100
  • Framing, including piers, joists, hardware, drainage gravel,etc: $2300
  • Decking: Grade "B" redwood & screws: $2800
  • Finishing, including stain, repairing damaged sprinkler lines, electrical, new path edging, pavers & rock, etc: $2400

Soup to nuts, everything came in a little under $10k