Why bother with the lowrise lift?

Having a 2 and 4 post lift, If I were to do it again, I would do a 1 post storage, like this: https://aclifts.com/lifts/m-1-single-post-car-lift/

and a 2 post.

As to the excavation, think seriously about what Java said. On a slab that large we pour 4-6 pads on virgin ground(when we pour footing), and dry stack open core cement blocks to grade. When you pour the floor, they will fill in with concrete. I would aim to place them in the vicinity of the lifts.

I also made a "grade beam" when I poured my current garage, when we levelled the stone I left a channel 4" deeper across the floor, in the vicinity of the 2 post lift, so the concrete was 8" thick in this area. Extra rebar in channel, make sure contractor supports it in the concrete, not lying on the bottom.
__________________
Political polls are often to give you an opinion, not to find out what your opinion is - Scott Adams
Old 12-01-2019, 10:06 AM
  Pelican Parts Catalog | Tech Articles | Promos & Specials    Reply With Quote #26 (permalink)