.... Here is the foundation detail.



Very little of the dirt removed will go back into the hole--just around the footer walls. Most of the dirt will be used to build up the area in front of the garage to backfill a retaining wall.

For the foundation, we'll bring in gravel and sand per the drawing. I plan to substitute a 20-mil reinforced vapor barrier (from my old company's crawl space kit).
You might consider dropping the interior slab slightly below the top of the foundation wall... say, 1" at the (back) end and sloping it about 1/8" per foot down toward the door to drain.

If you ever contemplate spraying/washing/squeegeeing the floor in the future.

So the drywall is up off the floor.