Quote:
Originally Posted by madcorgi
.... Here is the foundation detail.
Very little of the dirt removed will go back into the hole--just around the footer walls. Most of the dirt will be used to build up the area in front of the garage to backfill a retaining wall.
For the foundation, we'll bring in gravel and sand per the drawing. I plan to substitute a 20-mil reinforced vapor barrier (from my old company's crawl space kit).
|
You might consider dropping the interior slab slightly below the top of the foundation wall... say, 1" at the (back) end and sloping it about 1/8" per foot down toward the door to drain.
If you ever contemplate spraying/washing/squeegeeing the floor in the future.
So the drywall is up off the floor.
FWIW