Wall forms went in last week atop the footer. There was a slight delay on the pour because the city inspector was concerned about the amount of rebar that would be required on the back wall which is 7 feet tall and unopposed, i.e., filled on only one side. So I had to peel off another couple hundred bucks to get expedited engineering done over the weekend so we could make schedule.

Engineering came back OK on the wall as reinforced, so pour happened today with a large boom angle over the top of the house.



The going forward plan is to frame the structure before the slab is poured. This will allow us to not worry about waiting for a clear stretch of weather for the slab pour. As confirmed during the pouring of the footers, rain drops make divots.