Well, here we are a month later and the job is about 85% done! The biggest hold up is the two windows that haven't come yet. Supposed to be here in 2 weeks. One was sized wrong and the other has a damaged spot that looks pretty bad. On the plus side, the sun room walls are done and the marble window sills are in place. I still have to take up the sun room floor tiles (a heat gun is your friend) and get the floor ready for ceramic tiles that look like stone and paint the outside deck and steps. The project manager has done a really good job and is about as frustrated with the delays as I am! More to come.