Quote:
Originally Posted by thor66
The cables are tensioned while the concrete is uncured but already poured??
|
We would have a deck pour on Tuesday and pull the cables on Friday. We'd have to wait until we get a 3-day break on the cylinders. If the cylinder breaks don't came up to the required PSI, we'd wait other day to pull.