Well… I was smart and called inspector who said no to soow through joists, only conduit.
In my head I had a beautiful symphony of symmetric traces and only 4 junction boxes. Was going to quite beautiful…
Now I need a junction box in each bay… two columns of alternating junction boxes. So it greatly simplifies the routing. Pisser I need 8 more boxes which is $160.
All the bits have been trickling in. Bugger is I can’t start assembling , drilling, etc until I’ve got all the bits. Plan to do most assembly on the ground. The thwn is supposed to arrive tomorrow but it’s holiday cooking.
I did cut and strip the soow. Got a big pile now. Each fixture gets 2’ to junction box. Super glad the soow fits the cable glands.
Never cut liquidtight before so I’ll need to mess with it. I’ve heard the #1 thing is put the cone on while it’s on the ground.
|