really OT, Microsoft Project problem

I've got a big project I need to manage. Seven main tasks over 4 years on an 800 line project plan I put together.

Each task is time spanned and not effort driven.
For instance, R&R carburetor. I give a span of two days. Now how do I actually assign 4 hours to do it in that time span and how to assign a resource to do it?

thanks