|
A couple of answers. We did have a written contract. It did not specify the duration however. The contract was required to remove and dispose of all waste materials (I paid for this also) this was spelled out in the contract.
They installed all of the flooring they were suposed to at the end of the job (~1050sq feet). It was not done correctly. I kinew there were problems, but I did not realize the extent of the problems.
We have a lot of pictures documenting the extent of the damage done to the house. I think I am in good shape for any real show down. Still, it is a pain in the butt.
__________________
04 R1100SA (Pacific Blue metalic)
99 R1100SA (black) -- Totalled
|