Quote:
Originally Posted by Porsche-O-Phile
You'd think an Inspector (especially one that failed 'em twice before) would catch that, but then again...
|
Why would he? This kind of stuff could only be seen in the rough if the ref. is wired into the lights.
Flatbutt,
There's a loose neutral somewhere. I don't think he would wire the ref. circuit onto the lighting cir. But then, these guys???
His work should be good for one year after final punch list and final payment. Final punch list should not have anything to do with final inspection. Call him back. We would accept final payment until the final punch list is finish between owner and contractor.