All of our PMs used to use Microsoft Project. We were actually looking at a Project Server, but decided against it. One of the biggest problems was the need to "dumb down" the reports for upper management. That was taking up considerable effort each week. We looked around and found an Open Source project called ]project-open[. That gave us the ability to create specialized dashboards for upper management that presented just the information they wanted in a manner that they could understand. It is a very flexible and powerful tool.