Looks like government work.
My wife and I just had to have a new sewer installed. the mainline at the street is about 14 ft below grade so some digging is involved.
The city hired my backhoe contractor to do the first 25 ft. I paid him to do the remaining 65 ft to my house.
The city portion (25 ft) took 3 days and a city crew of 4 guys plus a backhoe and a string of dumptrucks lined up on the road.
The private portion (65 ft was done by the same backhoe operator alone except for a 70 yr old helper with a shovel. The 2 guys did the 65 ft section in a day and a half.