Quote:
Originally Posted by GH85Carrera
Our most recent project was to fill level the dirt from this hole.
You can see the hat of the man standing in the hole. We had to have a new sewer line put in because the old one had an issue at the connection to the city main. That hole was 9 feet deep.
They did OK getting the dirt back in the hole but it was not level and it needed 30 rolls of sod to cove up.
|
It really bothers me to see pics like this. That excavation should be shored, or stepped wider below his chest height. A small cave in and he's dead, happened a few years back to a local excavator.
I will never allow my guys to work in a trench more than 4' deep.