Bag, mixer or ready mix in a buggy isn't your problem. You problem is your help. You need another person to help with the pour or finish the concrete. This is not really something you can do in a days. a 4' thick 10x12 slab is about 1.5 yard of concrete or about 90 bags of 60 lbs bag of concrete. Its no fun unless you are looking to punish yourself.
Why not jsut pour small footings and set a pier on top and run floor joist over girder and install plywood subfloor on top of that and put your lil' building on top of that. All that can be done in a day and the cost would be a couple hundred bucks
|