If you have most of the bids in hand for each trade and are just writing scopes and Subcontracts/purchase orders I would allow five weeks. If you need to bid the project out then add another six weeks assuming the bid documents are complete. The market is hot now so you will really have to work at it to generate bidder interest. Take care.
|