Maybe delete some importing stuff, post it and see if we can help you with it.

This is just a small part of our contract:

Contractor shall commerce the work no later than xx working days after the signing of this Agreement and shall complete the work no later then xxx days thereafter.
Should the contractor be delayed in completing the work by circumstances beyond his control, the time of the completion shall be extended for such time lost.

The actual Cost of the Work shall constitute the Guaranteed Maximum Price of ONE HUNDRED SEVENTEEN THOUSAND ONE HUNDRED SEVENTY DOLLARS AND NO CENT.

$ 117,170.00

In the event the Contractor shall produce the work in excess of the Guaranteed Maximum Price, the Contractor shall pay 100% of the excess out of his own funds.

Any additional work requested by the Owner outside the scope of this Agreement shall be evidenced in writing and signed by both parties.




The final payment, constituting of the unpaid balance and the guaranteed Maximum price, if any, shall be paid by the Owner to the Contractor when the Work is completed in accordance with the requirements of the Contract Documents; and the satisfactory correction of deficiencies as enumerated by a comprehensive final punch list as agreed upon by the Owner and Contractor not final inspection.